China-backed Yonggang Central Asia Iron and Steel builds steel complex in Jibek Joly SEZ, with 1 Mt first phase due in 2027

Yonggang Central Asia Iron and Steel LLP, the Kazakh subsidiary of China's Fujian Hengwang Investment Co., Ltd., is building a full-cycle steel complex in the Jibek Joly special economic zone in Zhambyl region's Shu district. Design capacity is up to 3 million tonnes of steel products a year, with a 1-million-tonne first phase due in 2027 and full capacity by 2029. Around 2,500 permanent jobs are expected. Project documentation describes natural-gas-based direct reduction and electric arc furnaces, while the Prime Minister's website refers to a hydrogen-based shaft furnace.

Machine translation; may contain errors.

China-backed Yonggang Central Asia Iron and Steel builds steel complex in Jibek Joly SEZ, with 1 Mt first phase due in 2027

A full-cycle steel complex is under way in the Jibek Joly special economic zone in the Shu district of Zhambyl region. The investor is China's Fujian Hengwang Investment Co., Ltd., and the project is being implemented by its Kazakh subsidiary Yonggang Central Asia Iron and Steel LLP, which has been granted SEZ participant status (unconfirmed).

According to the Prime Minister's website, an investment agreement has been signed, and the industrial zone already has rail tracks, power lines and access to natural gas. The project has two stages; the complex is scheduled to start operating in 2027, followed by two years of expansion to up to 3 million tonnes of products a year.

Qazba.kz, citing the scoping conclusion of the project's environmental impact assessment, reported that the first phase will have a capacity of 1 million tonnes a year and the second up to 3 million tonnes. Construction is planned for 2026–2029, with the first phase commissioned in 2027, the second by 2029, and operations lasting at least 25 years.

The process chain in the project documentation runs from iron ore preparation and beneficiation through pelletising, natural-gas-based direct reduced iron (DRI), electric arc furnace steelmaking, refining and continuous casting to rolling. Main products are rebar, sections, profiles and strip. Metafront, citing documents released by environmental authorities, likewise describes a natural-gas DRI and electric furnace route. The Prime Minister's website says otherwise, describing it as the country's first steel complex using a hydrogen-based shaft furnace. The discrepancy has not been resolved.

The Prime Minister's website says about 1,500 temporary workers will be hired during construction and more than 2,500 permanent staff after commissioning; Metafront, citing the Zhambyl regional government, also puts permanent jobs at around 2,500. (unconfirmed) The same government source says the company plans to hire at least 90% of its staff locally.

(unconfirmed) Investment figures vary: the Prime Minister's website gives a total of US$756 million; National Business and Kursiv reported in September that the figure had risen to US$1.2 billion, both citing the same Qazba material; Metafront, citing regional authorities, gives KZT 564 billion.

Rules related to this news

(unconfirmed) Kursiv reported that a 350 MW gas turbine power plant is planned for the second stage, and that the complex will use iron ore from Karaganda, Kostanay and Ulytau regions. Metafront, citing contractor Hebei Metallurgical Construction Group, said the first steel column of the reformer was erected on August 30, marking the start of main equipment installation.

The investor chose the SEZ for its tax incentives and preferences (unconfirmed). The legal basis is the Law on Special Economic and Industrial Zones (No. 242-VI).

This is a steelmaking project that will smelt Kazakh iron ore into steel, not a mining project. In the newsroom's view, for Chinese steel and equipment companies the project matters as a chain that turns Kazakh ore into steel inside the country; the process route and final investment figure still await a consistent position from the investor.

Check the sources behind the policy, and let us connect you with the right people on the ground – ask tumah.kz for details

Sources:
- Official website of the Prime Minister of Kazakhstan: https://primeminister.kz/ru/news/realizatsiya-investproekta-kak-stroitsya-novyy-zavod-po-proizvodstvu-stali-v-zhambylskoy-oblasti-30164
- Qazba.kz, Sep 22, 2026: https://qazba.kz/metallurgiya/too-yonggang-central-asia-iron-and-steel-planiruet-zapustit-v-2027-godu-pervuyu-ochered-metkombinata/
- National Business, Sep 22, 2026: https://nationalbusiness.kz/news/kitaytsi-zapustyat-v-kazahstane-noviy-metallurgicheskiy-kombinat-za-12-mlrd-6fc116/
- Kursiv, Sep 22, 2026: https://kz.kursiv.media/2026-09-22/zhnb-moshhnyi-metallurgicheskii-kombinat-zapustit-kitai-v-zhambylskoi-oblasti/
- Metafront, Sep 15, 2026: https://metafront.news/kazakhstan-begins-full-scale-installation-of-3-million-ton-dri-steel-plant-phase-1-to-start-operations-in-2027/
Original: "According to the government of Zhambyl Region … Total investment is set at 564 billion tenge, with the plant expected to create around 2,500 permanent jobs once operational." / "PAF (Pan Asia Forward), the organization supporting the project, has put total investment at around 1.2 billion dollars. The project is expected to create around 1,500 jobs during construction and more than 2,500 jobs after the plant becomes operational."
Note: Metafront does not cite Qazba or mention the EIA; it describes the process route from "project documents released by Kazakhstan's environmental authorities" and attributes the jobs and investment figures to the Zhambyl regional government and PAF (Pan Asia Forward).
- Law on Special Economic and Industrial Zones (adilet Z1900000242): https://adilet.zan.kz/rus/docs/Z1900000242

(This article was prepared with AI assistance and reviewed by an editor; the illustration is AI-generated and is not a photograph.)

Key facts

  • 永钢中亚钢铁 is building a fully integrated steel complex in the Jibek Joly Economic Zone in Shushi District, Zhambyl Region.
  • Phase I has an annual capacity of 1 million tonnes and is scheduled to commence operations in 2027; Phase II is planned to commence operations before 2029.
  • The project is designed for final annual output of up to 3 million tonnes, with products including rebar, structural sections, wire rod, and strip steel.
  • The environmental impact assessment documents list natural gas-based direct reduced iron combined with electric arc furnace steelmaking, while the Prime Minister's official website states that a hydrogen-based shaft furnace will be used.
  • The project is planned to use Kazakhstan iron ore as feedstock and convert it locally into steel for construction and industrial use.
  • The legal basis for the economic zone project is Article 242-VI of the Law on Economic Zones and Industrial Zones.

FAQ

Who is developing the project, and where is it located?

The project is being developed by 永钢中亚钢铁 in the Jibek Joly Economic Zone in Shushi District, Zhambyl Region. 永钢中亚钢铁 is a subsidiary of 福建恒旺投资 in Kazakhstan.

When will the project commence operations, and how will capacity be planned?

Phase I has an annual capacity of 1 million tonnes and is scheduled to commence operations in 2027; Phase II will expand the annual capacity to a maximum of 3 million tonnes and is planned to commence operations before 2029.

Which steelmaking process will the project use?

The environmental impact assessment documents list a natural gas-based direct reduced iron process and an electric arc furnace steelmaking route, while the Prime Minister's official website states that a hydrogen-based shaft furnace will be used. The two descriptions have not yet been reconciled.

What is the investment amount?

The publicly available figures are inconsistent: the Prime Minister's official website cites USD 756 million, National Business and Kursiv cite USD 1.2 billion, and Metafront, citing the regional government, gives KZT 564 billion. A unified figure still needs to be confirmed by the project developer.

Has 永钢中亚钢铁 already been granted participant status in the economic zone?

The source text states that 永钢中亚钢铁 has been granted participant status in the economic zone, but this claim has been flagged as questionable. Article 242-VI of the Law on Economic Zones and Industrial Zones is the relevant legal basis.

Legal basis
《哈萨克斯坦共和国经济特区和工业区法》(第242-VI号,adilet Z1900000242,现行有效),Jibek Joly经济特区参与者身份及税收优惠的法律依据。
primeminister.kz/ru/news/realizatsiya-investproekta-kak-stroitsya-novyy-zavod-po-proizvodstvu-stali-v-zhambylskoy-oblasti-30164 The official text on adilet.zan.kz prevails.
Ask a question Every answer cites its source; if we cannot answer, a person replies within 24 hours.