资料截至2026年11月8日(依据哈萨克斯坦司法部规范性法律文件信息系统现行有效法规条文:哈萨克斯坦可再生能源支持法)。
问:中企参与哈萨克斯坦风电、光伏电站投资,如何法定获取购电协议签约资格?
答:外资企业参与哈萨克斯坦集中式可再生能源开发,主要通过国家组织的公开电子拍卖竞价流程获取开发配额与购电协议签署权。依据哈萨克斯坦可再生能源支持法及哈萨克斯坦能源部关于批准拍卖交易组织与实施规则的第466号部令,拍卖由指定拍卖操作机构主持,竞价上限执行官方设定的最高拍卖限价。竞标主体通过低价竞争胜出后,方可列入可再生能源发电商名录,并取得与国家设立的单一买方机构——可再生能源支持结算财务中心(RFC)签订长期购电协议(PPA)的资格。
问:签订长期购电协议(PPA)有哪些核心履约要求与财务担保门槛?
答:依据哈萨克斯坦能源部关于批准购电标准合同范本的第480号部令,中标企业须在法定期限内向结算财务中心提交签约申请并签署标准格式PPA。合同履约机制要求开发商提供法定形式的财务履约担保(如符合资质的银行保函),以担保电站按期完成建设与投入商业运营。若项目未能在合同规定期限内完成建设并网,相关履约担保面临被扣减或合同终止的法定后果。
问:电站接入电网与取得技术许可(TU)遵循何种法定流程?
答:根据哈萨克斯坦电力法,可再生能源发电设施接入国家统一电力系统,必须向对应的电网运营企业(国家电网输电运营主体或区域配电公司)申请接入电网技术规范条件(TU)。电网企业依据区域电网承载能力核发技术条件,明确具体并网接入点及受电变电站。项目开发方需依据技术条件自行出资设计、建设送出线路及配套升压并网工程,并在验收合格后办理并网调度联调手续。
Rules related to this news
- Renewable energy auction PPA 20 years KazakhstanRES projects selected at auctions sign a 20-year power purchase agreement with the single buyer, which is responsible …Text and legal basis →
- Kazakhstan renewable energy capacity 2025At end-2025 renewable capacity was 3,749.6 MW (wind 2,059, solar 1,375, hydro 314, biogas 1.8) across 169 plants; rene…Text and legal basis →
问:新能源电站并网后的电量消纳与电力调度地位如何界定?
答:依据哈萨克斯坦可再生能源支持法与哈萨克斯坦能源部关于批准单一买方集中买卖可再生能源电力规则的第164号部令,哈萨克斯坦国家电力系统对合规入网的可再生能源发电实行优先调度与输送机制。单一买方(结算财务中心)依照法规负责集中统一收购可再生能源发电设施所发出的全部上网电量,电网企业在维持电网安全运行前提下提供优先输送服务。
问:电费结算机制如何运作,通胀与汇率变动如何处理?
答:依据哈萨克斯坦能源部关于批准购电标准合同范本的第480号部令以及哈萨克斯坦能源部关于批准单一买方集中买卖可再生能源电力规则的第164号部令,电费结算周期按月进行,单一买方依据双方核准的商业计量表计数据,以哈萨克斯坦法定货币坚戈(KZT)向发电企业支付购电款。为缓解宏观经济波动影响,PPA合同明确设立年度电价指数化调整机制,在法定期限内依据官方发布的通货膨胀率与汇率变动参数对拍卖中标电价进行相应调整。
政策能查出处,落地找人对接,详情问 tumah.kz。
封面图片由AI生成,非真实照片。
Key facts
- Development quotas for utility-scale renewable energy projects in Kazakhstan and the right to sign power purchase agreements are obtained through public electronic auctions.
- Winning companies must provide financial performance security in the legally prescribed form to secure the timely completion and commercial operation of the power plant.
- Project developers in Kazakhstan must themselves construct transmission lines and associated step-up and grid connection facilities in accordance with the grid technical conditions.
- Kazakhstan's national power system grants priority dispatch and transmission to compliant, grid-connected renewable generation.
- The Financial Settlement Centre for Renewable Energy Support pays for electricity monthly in tenge based on approved metering data.
- The power purchase agreement includes an annual electricity price indexation mechanism, under which the awarded tariff is adjusted according to the officially published inflation rate and exchange rate fluctuation parameters.
FAQ
How can Chinese enterprises developing utility-scale wind and solar projects in Kazakhstan become eligible to sign power purchase agreements?
Eligibility is obtained mainly by winning a bid in the publicly organized electronic auction conducted by the state to secure a development quota. After the successful bidder is included in the register of renewable energy generators, it becomes eligible to enter into a power purchase agreement with the Financial Settlement Centre for Renewable Energy Support.
What performance and financial security requirements must be met when signing a power purchase agreement?
The winning company must submit an application for contracting within the statutory period, sign the standard-form power purchase agreement, and provide financial performance security in the legally prescribed form. Failure to complete construction and grid connection within the contractually prescribed period will result in the statutory consequences of the performance security being drawn down or the contract being terminated.
How do renewable energy plants apply for grid connection technical conditions?
The project must apply to the relevant grid operator for the technical specifications and conditions for connection to the grid, which the grid operator issues based on the hosting capacity of the regional grid. The project developer must finance and construct the transmission line and associated step-up and grid connection facilities itself and, after they pass acceptance inspection, complete the joint commissioning and dispatch procedures for grid connection.
How are electricity offtake and power dispatch determined after a plant is connected to the grid?
Kazakhstan's national power system grants priority dispatch and transmission to compliant, grid-connected renewable generation. The Financial Settlement Centre for Renewable Energy Support acts as the centralized buyer of all electricity generated by the relevant facilities and fed into the grid, while grid operators provide priority transmission services, provided that safe operation is ensured.
How are power purchase payments settled, and how do inflation and exchange rate changes affect electricity prices?
Power purchase payments are settled monthly, with the Financial Settlement Centre for Renewable Energy Support making payment in tenge, Kazakhstan's legal tender, based on data from approved commercial meters. The power purchase agreement includes an annual electricity price indexation mechanism, under which the awarded tariff is adjusted according to the officially published inflation rate and exchange rate fluctuation parameters.