The initiative represents one of Qarmet's largest investment projects. According to the official report, coke production facilities of comparable scale have not been constructed at the plant for decades.
What are the technical parameters of the new coke batteries?
According to the official website of the President of Kazakhstan, the two batteries are planned to start up in 2027 and, once operating, to produce 1.5 million tonnes of dry coke per year in total. Each battery includes 54 coke ovens with chambers measuring 7.6 meters in height.
ACRE Coking & Refractory Engineering Consulting Corporation serves as the general technological partner for the project.
Why is Qarmet constructing new coke batteries?
The commissioning of the new equipment is intended to improve the reliability of self-sufficient coke supplies for blast furnace production, maintain stable coke quality, and ensure higher environmental safety standards. The new units will replace obsolete facilities installed between 1960 and 1970.
When will the project be commissioned?
According to the presidential website, the launch of the batteries is planned for 2027. The report noted that following completion, Kazakhstan will establish its first coal chemical complex for deep processing of coking by-products.
FAQ
### What annual output is expected from the new coke batteries once they are operating?
According to the presidential website, the two batteries are planned to start up in 2027 and, once operating, to produce 1.5 million tonnes of dry coke per year in total.
Rules related to this news
- What is the Korkyt Ata SEZ in Kyzylorda?The Korkyt Ata SEZ was created by Government Decree No.Text and legal basis →
- Can a plant in Kazakhstan use summarized working time, and for how long a period?Summarized working time may be used in continuous production and work where daily or weekly hour limits cannot be met;…Text and legal basis →
- China Kazakhstan joint projects numberThe two countries are implementing 260 large joint projects worth over USD 62 bn; the project pipeline holds 329 proje…Text and legal basis →
### How many ovens are in each battery?
Each battery consists of 54 ovens with a chamber height of 7.6 meters.
### When is the commissioning planned?
According to the presidential website, commercial launch is planned for 2027.
### Which facilities will the new equipment replace?
According to the presidential website, the project replaces aging production capacities built between 1960 and 1970.
### Is this news related to China?
The source does not mention Chinese companies, and no conclusions are drawn in the article.
Related reading
- More industry and policy developments: Kazakhstan investment and project news
- Qarmet: Qarmet signs steel export agreement with Traxys
- Qarmet: Public hearing on mining operations plan for Qarmet's Tentekskaya mine
- Setting up a project company in Kazakhstan: Company registration services in Kazakhstan
Sources
- Official website of the President of the Republic of Kazakhstan via the Karaganda Region page (gov.kz), November 2: https://www.gov.kz/memleket/entities/karaganda/press/news/details/1322043?lang=ru
Illustration: AI-generated, not a real photograph.