Kazakhstan's Tau-Ken Samruk has launched a tender to sell a 51% to 100% stake in ShalkiyaZinc for no less than 174.2 billion tenge. The Ministry of Energy reported a 10-month electricity generation of 102.4 billion kWh, oil product reserves reaching 1.2 million tons, and 112 subsoil blocks put up for electronic auction. Officials also coordinated commercial terms for the Karachaganak gas processing plant with a capacity of up to 5 bcm.

Machine translation; may contain errors.

Kazakhstan Mining and Energy News Roundup

Illustration: AI-generated, not a real photo.

Information current as of November 17, 2026, 00:30 (Asia/Almaty); source dates are indicated in the text

Kazakhstan Mining and Energy News Roundup

Kazakhstan's mining and energy sectors have recently witnessed several major asset restructuring and project advancement initiatives. The national mining company has formally launched the procedure to transfer a controlling stake in a key domestic zinc-lead mining asset; the President has outlined instructions regarding follow-up measures on reliable energy supply and related matters; the Ministry of Energy has placed 112 subsoil use blocks onto an electronic auction platform; concurrently, competent authorities continue to advance preliminary technical and commercial coordination for supporting processing facilities at major gas fields.

National Mining Company Launches Open Two-Stage Tender for Sale of Shalkiya Zinc-Lead Mine Shares

According to the privatization section and official announcements on the website of Tau-Ken Samruk National Mining Company, the company has formally announced the sale of 51% to 100% of ordinary voting shares held in ShalkiyaZinc LTD JSC through an open two-stage tender process. The announcement states that the tender is scheduled to commence on November 13, 2026, at 09:00 (Astana time) at 17/10 Syganak Street, Astana Tender Notice Document. The transaction is conducted pursuant to the "Rules for Transfer of Assets of Sovereign Wealth Fund 'Samruk-Kazyna' Joint Stock Company and Organizations More Than Fifty Percent of Voting Shares (Participating Interests) in Which Directly or Indirectly Belong to It into a Competitive Environment" (approved by decision of in-absentia meeting No. 181, as amended and supplemented by protocol minutes Nos. 183, 187, 202, 219, 228, 234, 236, 261, 265, and 280, specifying that the Russian version shall prevail) Tender Notice Document. The announcement notes that the Shalkiya deposit, located in the Zhanakorgan District of Kyzylorda Region, is Kazakhstan's largest zinc deposit, accounting for approximately half of the nation's zinc reserves, with a design mining capacity of approximately 4 million tons of ore per year and projected design metal recovery rates of approximately 75% for zinc and approximately 50% for lead Tender Notice Document.

The announcement stipulates that the total transaction value shall not be less than 174,219,747,063.29 tenge, consisting of two components: the starting price for 100% of the target asset's ordinary shares is 86,960,000,000 tenge (calculated pro rata to the actual proportion of shares acquired); and the total principal and interest on loan agreement debt owed by the target asset to the seller as of September 30, 2026, of not less than 87,259,747,063.29 tenge (to be recalculated on the actual debt settlement date) Tender Notice Document. Potential participants must submit a security deposit of 500 million tenge prior to the application deadline as security for the application and contract performance (non-residents may pay in US dollars at the central bank exchange rate on the date of payment) and sign a non-disclosure agreement to obtain access to the virtual data room. The deadline for receiving Stage One applications is December 25, 2026, at 10:00 (Astana time). After review for compliance and qualification approval, participants proceed to Stage Two to submit tender bids containing price and share purchase conditions Tender Notice Document. Key considerations for Chinese enterprises: the announcement specifies that in case of discrepancies, the Russian version prevails and no translation services are provided; participants must sign a non-disclosure agreement in accordance with regulations, pass qualification reviews, and pay the security deposit in full before the deadline.

President Tokayev Receives Report from Energy Minister on Ten-Month Operations of Fuel and Energy Complex

Rules related to this news

According to information released by the Ministry of Energy of Kazakhstan on November 16, Head of State Tokayev received a report from Minister of Energy Akkenzhenov regarding the primary development achievements of the fuel and energy complex in the first ten months of this year, the progress of the heating season, and upcoming plans Ministry of Energy of Kazakhstan. Power plant repair funding increased to 384 billion tenge, the number of power plants in the "red risk zone" decreased to 5, and national power generation grew by 2.3% during the first ten months to reach 102.4 billion kilowatt-hours Ministry of Energy of Kazakhstan. Oil processing volume increased by 4.7%, and total commercial petroleum product reserves rose to 1.2 million tons; domestic bitumen production reached 1.1 million tons; the expansion of the Shymkent Oil Refinery to an annual processing capacity of 12 million tons and a new petrochemical complex project in Atyrau Region are currently in progress Ministry of Energy of Kazakhstan.

In the natural gas sector, the residential gasification rate is projected to reach 64.5% by the end of the year, providing 13.2 million citizens with gas access; new gas processing plants at Kashagan and Zhanaozen are under construction, and EPC contracts have been signed for Karachaganak and Kashagan Phase Two projects Ministry of Energy of Kazakhstan. To stimulate geological exploration, the Ministry of Energy has placed a record 112 subsoil use blocks onto the electronic auction platform, and has initiated an update of the national Unified Energy Balance (up to 2035) that factors in demand from high-energy data centers and artificial intelligence computing infrastructure Ministry of Energy of Kazakhstan.

Ministry of Energy Convenes Coordination Meeting on Karachaganak Gas Processing Plant Project

According to information released by the Ministry of Energy of Kazakhstan on November 12, Vice Minister Tutkishbayev chaired a construction coordination meeting for the Karachaganak gas processing plant project, which has an annual processing capacity of up to 5 billion cubic meters Ministry of Energy of Kazakhstan. Representatives from national gas company QazaqGaz, shareholders of the Karachaganak project, the West Kazakhstan Regional Akimat, and the PSA Authority participated to discuss early engineering design progress, gas pipeline construction, grid tie-in point selection, and the establishment of raw gas metering systems Ministry of Energy of Kazakhstan. The meeting focused on reviewing and coordinating commercial terms, covering key topics including the Evacuation Service Agreement, Evacuation Service Fee rates, and raw gas transfer conditions Ministry of Energy of Kazakhstan.

Source List
- Publisher: Tau-Ken Samruk Official Website Privatization Section, Date: 2026-11-13, Link: https://tks.kz/en/privatization/
- Publisher: Tau-Ken Samruk Tender Notice Document, Date: 2026-11-14, Link: https://tks.kz/wp-content/uploads/2026/11/Notification-Of-Tender.docx
- Publisher: Ministry of Energy of the Republic of Kazakhstan, Date: 2026-11-16, Link: https://www.gov.kz/memleket/entities/energo/press/news/details/1330599?lang=ru
- Publisher: Ministry of Energy of the Republic of Kazakhstan, Date: 2026-11-12, Link: https://www.gov.kz/memleket/entities/energo/press/news/details/1328221?lang=ru

政策能查出处,落地找人对接,详情问 tumah.kz
Policies can be traced to their sources, implementation contacts can be arranged — ask tumah.kz for details

Key facts

  • The Kazakhstan National Mining Company is selling a 51% to 100% interest in the ordinary shares of Shalkiya Zinc JSC through a public two-stage tender.
  • The total transaction value of the Shalkiya Zinc JSC equity tender is no less than KZT 174,219,747,063.29.
  • The Shalkiya deposit is located in Zhanakorgan District, Kyzylorda Region, and accounts for approximately half of Kazakhstan’s zinc reserves.
  • The Ministry of Energy of Kazakhstan has listed 112 subsurface resource blocks on the electronic auction platform.
  • National electricity generation in Kazakhstan increased by 2.3% in the first ten months to 102.4 billion kWh.
  • The Karachaganak Gas Processing Plant has a maximum annual processing capacity of 5 billion cubic metres, and the relevant authorities are coordinating the terms of commercial cooperation.

FAQ

What stake in Shalkiya Zinc JSC is being sold in this tender?

The Kazakhstan National Mining Company is selling, through a public two-stage tender, a 51% to 100% interest in the ordinary shares of Shalkiya Zinc JSC that it holds.

What is the transaction value of the Shalkiya Zinc JSC equity transaction?

The announcement specifies a total transaction value of no less than KZT 174,219,747,063.29, comprising the starting price for 100% of the ordinary shares and the outstanding principal and interest under the loan agreement as of September 30, 2026; the final debt amount will be recalculated on the repayment date.

What conditions must be met to participate in the Shalkiya equity tender?

The Russian-language version of the announcement shall prevail, and no translation service is provided. Potential participants must sign a confidentiality agreement, pass the qualification review, and pay a collateral deposit of KZT 500 million before the application deadline; the deadline for accepting applications is December 25, 2026, at 10:00 (Astana time).

What recent mining and energy transaction information is available in Kazakhstan?

The Ministry of Energy of Kazakhstan has listed 112 subsurface resource blocks on the electronic auction platform. Nationwide electricity generation increased by 2.3% in the first ten months to 102.4 billion kWh, while combined refined oil reserves rose to 1.2 million tonnes.

What matters were addressed by the coordination meeting for the Karachaganak Gas Processing Plant project?

A construction coordination meeting was held for the Karachaganak Gas Processing Plant project, which has a maximum annual processing capacity of 5 billion cubic metres. The meeting reviewed the feed gas export service agreement, the fee schedule for export services, and the handover conditions for feed gas.